July 31, 2020
Pandangan udara penutupan bumbung di kekotak stesen dan kerja-kerja konkrit tetulang di pintu masuk sedang dijalankan di tapak Stesen MRT Putrajaya Sentral.

Putrajaya Sentral

Aerial view of the roof covering at the station box and reinforced concrete works at entrance in progress at the Putrajaya Sentral MRT Station site
July 23, 2020
Pandangan udara tapak Stesen MRT Jalan Ipoh menunjukkan kerja-kerja penggalian, sengkang dan pembinaan papak asas sedang dijalankan.

Jalan Ipoh (Jalan Ipoh)

Aerial view of the Jalan Ipoh MRT Station site showing the excavation works, strutting and base slab construction in progress.
June 30, 2020
Pandangan kerja-kerja landasan sedang dijalankan di jajaran berhampiran tanjakan ke Tol Sungai Buloh.

PLUS Highway (Sg Buloh Toll)

View of the ongoing trackworks at the alignment near ramp to Sungai Buloh Toll.
June 30, 2020
Pandangan kerja-kerja luaran fakad sedang dijalankan untuk Pintu Masuk 1 dan 2 Stesen MRT Damansara Damai.

Jalan Kuala Selangor (Damansara Damai)

View of the external façade works in progress for Damansara Damai MRT Station entrance 1 and 2.
June 30, 2020
Pemasangan laluan pejalan kaki berbumbung sedang dijalankan di tapak Stesen MRT Sri Damansara Barat.

Persiaran Dagang (Sri Damansara Sentral)

Covered walkway installation in progress at the Sri Damansara Barat MRT Station site.
June 30, 2020
Pandangan udara Stesen MRT Sri Damansara Timur menunjukkan pemasangan panel logam yang diperluas berhampiran KTMB telah siap.

Jalan Kepong (Sri Damansara Timur)

Aerial view of the Sri Damansara Timur MRT Station showing the completed installation of expanded metal panel near KTMB.
June 30, 2020
Pandangan udara tapak Stesen MRT Kepong Baru menunjukkan pemasangan tiang untuk laluan pejalan kaki berbumbung dan kerja-kerja jalan sedang dijalankan

Jalan Kepong (Kepong Baru)

Aerial view of the Kepong Baru MRT Station site showing the installation of columns for covered walkway and roadworks in progress.
June 30, 2020
Pandangan udara tapak Stesen MRT Jinjang menunjukkan kerja-kerja struktur Pintu Masuk 1 dan 2 sedang dijalankan.

Jalan Kepong (Jinjang)

Aerial view of the Jinjang MRT Station site showing Entrance 1 and 2 structural works in progress.
June 30, 2020
Kerja-kerja saliran sedang dijalankan di Stesen MRT Sri Delima.

Jalan Kepong (Sri Delima)

Drainage works in progress at the Sri Delima MRT Station