October 31, 2019
Pandangan udara tapak Stesen MRT Seri Kembangan menunjukkan kerja-kerja pembinaan galang kekotak bersegmen sedang berjalan.

Seri Kembangan

Aerial view of Seri Kembangan MRT Station site showing the erection works for segmental box girder in progress.
October 31, 2019
Pandangan tanah Depoh Serdang menunjukkan bangunan pejabat pentadbiran dan kerja pengukuhan untuk rasuk bumbung sedang dijalankan.

Serdang Depot

Ground view of the Serdang Depot showing the administration office building and reinforcement work for roof slab in progress.
October 31, 2019
Pandangan udara tapak Stesen MRT Taman Equine menunjukkan rasuk aras tengah yang telah siap dan sokongan sementara untuk aras platform sedang dijalankan.

Equine Park

Aerial view of the Equine Park MRT Station site showing the completed intermediate level slab while temporary support to platform level in progress.
October 31, 2019
Pandangan udara rasuk aras ruang legar sedang dijalankan di tapak Stesen MRT Taman Putra Permai.

Taman Putra Permai

Aerial view of ongoing concourse level slab at the Taman Putra Permai MRT Station site.
October 31, 2019
Pandangan udara tapak Stesen MRT 16 Sierra menunjukkan pemasangan lapik bumbung lapisan terakhir dan Pintu Masuk 2 sedang dijalankan.

Persiaran Sierra Utama (16 Sierra)

Aerial view of the 16 Sierra MRT Station site showing the final layer and Entrance 2 roof covering installations in progress.
October 31, 2019
Kerja-kerja bongkah aras ruang legar sedang dijalankan di tapak Stesen MRT Cyberjaya Utara.

Persiaran APEC (Cyberjaya North)

Ongoing concourse level blockworks at the Cyberjaya North MRT Station site.
October 31, 2019
Pandangan udara Stesen MRT Cyberjaya City Centre menunjukkan struktur bumbung besi sedang dijalankan.

Persiaran APEC (Cyberjaya City Centre)

Aerial view of the Cyberjaya City Centre MRT Station showing the roof steel structure in progress.
September 30, 2019
Pandangan udara persilangan rentang panjang jejambat yang telah siap di jajaran berhampiran tanjakan ke Tol Sungai Buloh.

PLUS Highway (Sg Buloh Toll)

Aerial view of the completed long span crossing viaduct at the alignment near ramp to Sungai Buloh Toll.
September 30, 2019
Pandangan udara persiapan kerja-kerja luaran Stesen MRT Damansara Damai sedang berjalan.

Jalan Kuala Selangor (Damansara Damai)

Aerial view of Damansara Damai MRT Station external works preparation in progress.