January 31, 2019
Kerja-kerja penyiapan untuk pembinaan tiang di jajaran menyeberangi Jalan Kuching di Stesen MRT Sri Delima.

Jalan Kepong (Sri Delima)

Finishing works of pier construction for the alignment crossing Jalan Kuching at the Sri Delima MRT Station
January 31, 2019
Kerja-kerja pembinaan tukup cerucuk sedang berjalan di sepanjang Jalan Ipoh berdekatan tapak Stesen MRT Kentomen.

Jalan Ipoh (Kentonmen)

Pile cap construction works in progress along Jalan Ipoh near the Kentonmen MRT Station site.
January 31, 2019
Kerja-kerja cerucuk gerek sekan sedang dijalankan di hadapan Kompleks Mutiara untuk Stesen MRT Jalan Ipoh.

Jalan Ipoh (Jalan Ipoh)

Ongoing secant bore piling works in front of Mutiara Complex for Jalan Ipoh MRT Station.
January 31, 2019
Kerja-kerja tanah sedang dijalankan di tapak Stesen MRT Conlay.

Jalan Conlay (Conlay)

Ongoing earthwork at Conlay MRT Station site.
January 31, 2019
Kerja-kerja pemasangan rebar sedang berjalan di tapak Syaf Penyelenggaraan 2.

Kampung Pandan Roundabout (Intervention Shaft 2)

Erection of rebar works in progress at the Intervention Shaft 2 site.
January 31, 2019

Jalan Peel (Escape Shaft 3)

Ongoing curing works as well as dismantling formwork activities at the Escape Shaft 3 site.
January 31, 2019
Pandangan udara tapak Syaf Penyelenggaraan 3.

Jalan Chan Sow Lin (Intervention Shaft 3)

Aerial view of the Intervention Shaft 3 site.
January 31, 2019
Kerja-kerja penggalian dan penguatan batu sedang dijalankan di tapak Stesen MRT Chan Sow Lin.

Jalan Chan Sow Lin (Chan Sow Lin)

Rock strengthening and excavation works being carried out at the Chan Sow Lin MRT Station site.
January 31, 2019
Pandangan udara kerja-kerja yang berjalan untuk pembinaan tiang, portal dan kepala tiang di tapak Stesen MRT Kuchai Lama.

Jalan Kuchai Lama (Kuchai Lama)

Aerial view of the ongoing pier, portal and pier head construction works at the Kuchai Lama MRT Station site.