February 28, 2019
Pandangan udara kepala tiang yang telah siap di persilangan Lebuhraya Putrajaya-Cyberjaya.

Putrajaya-Cyberjaya Expressway

Aerial view of the completed pier heads at the alignment crossing Putrajaya-Cyberjaya Expressway.
February 28, 2019
Pelancaran Galang Kekotak Bersegmen sedang berjalan di tapak Stesen MRT Putrajaya Sentral.

Putrajaya Sentral

Segmental Box Girder launching in progress at the Putrajaya Sentral MRT Station site.
February 10, 2019
Pembinaan segmen pratuang lintasan rentang panjang sedang dijalankan berhampiran dengan tanjakan ke Tol Sungai Buloh

PLUS Highway (Sg Buloh Toll)

Erection of long span crossing precast segments in progress near the ramp to Sungai Buloh Toll.
January 31, 2019
Penyiapan pembinaan galang kekotak bersegmen menggunakan kaedah tresel di jajaran laluan Sungai Buloh-Serdang-Putrajaya berhampiran dengan Sekolah Antarabangsa IGB.

Jalan Kuala Selangor (IGB International School)

Completion of segmental box girder erection using trestle at the Sungai Buloh-Serdang-Putrajaya Line alignment near IGB International School.
January 31, 2019
Pembinaan galang kekotak bersegmen sedang dijalankan bagi lintasan rentang panjang no. 1 di Sungai Gasi berhampiran Plaza Tol Sungai Buloh.

PLUS Highway (Sg Buloh Toll)

Segmental box girder erection for long span crossing no. 1 in progress at Sungai Gasi near the Sungai Buloh Toll
January 31, 2019
Kerja-kerja pemasangan kekuda bumbung sedang dijalankan di tapak Stesen MRT Damansara Damai.

Jalan Kuala Selangor (Damansara Damai)

Ongoing roof truss installation works at the Damansara Damai MRT Station site.
January 31, 2019
Kerja-kerja persediaan pelancar Rasuk berbentuk T sedang dijalankan di tapak Stesen MRT Sri Damansara Barat

Jalan Kuala Selangor (Sri Damansara West)

Preparation of T-Beam launching in progress at the Sri Damansara West MRT Station site.
January 31, 2019
Pembinaan galang kekotak bersegmen bagi lintasan panjang No.3 di persilangan antara LDP, DUKE dan MRR2 berhampiran dengan tapak Stesen MRT Sri Damansara Timur

Persiaran Dagang (Sri Damansara East)

Segmental Box Girder erection for long span crossing no.3 at the LDP, DUKE and MRR2 interchange near Sri Damansara East MRT Station site.
January 31, 2019
Pandangan udara pelancaran galang kekotak bersegmen sedang dijalankan di tapak Stesen Kepong Sentral. Kelihatan juga kerja-kerja pembinaan dinding peparit, rasuk dan papak bagi aras bawah di Pencawang Kuasa Tarikan.

Jalan Kepong (Kepong Sentral)

Aerial view of segmental box girder launching in progress at the Kepong Sentral MRT Station site. Also seen is the construction works for trench wall, beam and slab for the ground level at Traction Power Substation.