February 12, 2017
View of ongoing site preparation works within site for the construction of the Cross Over Box/Intervention Shaft 1.

Lorong Raja Muda Abdul Aziz

View of ongoing site preparation works within site for the construction of the Cross Over Box/Intervention Shaft 1.
February 11, 2017
Secant Bored Pile excavation and Diaphragm Wall works ongoing at the future Titiwangsa MRT Station construction site.

Jalan Tun Razak (Titiwangsa)

Secant Bored Pile excavation and Diaphragm Wall works ongoing at the future Titiwangsa MRT Station construction site.
February 10, 2017
Preparation for traffic diversion for the construction of the future Sentul West Station at Jalan Sultan Azlan Shah.

Jalan Sultan Azlan Shah (Sentul West)

Preparation for traffic diversion for the construction of the future Sentul West Station at Jalan Sultan Azlan Shah.
January 18, 2017
MRT construction work at the future Bandar Malaysia North Station site.

Sungai Besi Airforce Base

MRT construction work at the future Bandar Malaysia North Station site.
January 17, 2017
New Jersey Barriers around the Escape Shaft 3 site at Jalan Peel that has been set up.

Jalan Peel (Escape Shaft 3)

New Jersey Barriers around the Escape Shaft 3 site at Jalan Peel that has been set up.
January 16, 2017
Ongoing preparation works at the Intervention Shaft 2 site at the Kampung Pandan Roundabout.

Kampung Pandan Roundabout (Intervention Shaft 2)

Ongoing preparation works at the Intervention Shaft 2 site at the Kampung Pandan Roundabout.
January 15, 2017
View of the future Conlay Station site with ongoing drainage works.

Jalan Conlay (Conlay)

View of the future Conlay Station site with ongoing drainage works.
January 14, 2017
Aerial view of ongoing works at the future Ampang Park MRT Station site.

Jalan Tun Razak (Ampang Park)

Aerial view of ongoing works at the future Ampang Park MRT Station site.
January 13, 2017

Lorong Raja Muda Abdul Aziz

Traffic diversion that has been implemented at the future Kampung Baru North Station site.