October 31, 2019
Kerja-kerja pemasangan membran kalis air dan pembinaan rebar untuk papak asas di tapak Syaf Penyelenggaraan 3.

Jalan Chan Sow Lin (Intervention Shaft 3)

Waterproofing membrane installation and rebar erection works for base slab at the Intervention Shaft 3 site.
October 10, 2019
Pandangan Mesin Pengorek Terowong S-775, sedang dalam proses bertukar dari mod Ketumpatan Pembolehubah ke mod Keseimbangan Tekanan Bumi, menggali dari Stesen MRT Conlay ke arah Stesen MRT Ampang Park.

Jalan Conlay (Conlay)

View of the S-775 Tunnel Boring Machine, in the process of converting from Variable Density mode to Earth Pressure Balance mode, mining from Conlay MRT Station towards Ampang Park MRT Station
September 30, 2019
Pandangan pemasangan rasuk gelang di dalam terowong di antara Stesen MRT Bandar Malaysia Utara dan Stesen MRT Chan Sow Lin.

Sungai Besi Air Force Base (Bandar Malaysia North)

View of the installation of ring beam in the tunnel between Bandar Malaysia North MRT Station and Chan Sow Lin MRT Station.
September 30, 2019
Pandangan udara kerja-kerja gali dan timbus di tapak Syaf Kecemasan 1.

Jalan Sultan Azlan Shah (Escape Shaft 1, North Portal)

Aerial view of the cut and cover works at Escape Shaft 1 site.
September 30, 2019
Pandangan pemasangan jadual kerja acuan papak isian aras bumbung di tapak Stesen MRT Titiwangsa.

Jalan Tun Razak (Titiwangsa)

View of the roof level infill slab formwork table installation at the Titiwangsa MRT Station site.
September 30, 2019
Pandangan malam tapak Stesen MRT Hospital Kuala Lumpur menunjukkan pembinaan dinding konkrit tetulang.

Jalan Tun Razak (Hospital Kuala Lumpur)

Night view of Hospital Kuala Lumpur MRT Station site showing reinforced concrete wall construction.
September 30, 2019
Pandangan penanggalan sedang dijalankan untuk mesin pengorek terowong selepas penembusan di Syaf Penyelenggaraan 1.

Jalan Tun Razak (Intervention Shaft 1)

View of the ongoing dismantling of tunnel boring machine after breakthrough at the Intervention Shaft 1.
September 30, 2019
Pandangan udara penggalian dinding gegendang Stesen MRT Kampung Baru Utara bermula di Pintu Masuk A.

Jalan Raja Muda Abdul Aziz (Kampung Baru North)

Aerial view of the excavation of diaphragm wall starting at Entrance A of the Kampung Baru North MRT Station.
September 30, 2019
Pandangan kerja-kerja penggalian syaf dan dinding pelapik konkrit tetulang sementara sedang dijalankan di tapak Syaf Kecemasan 2

Jalan Gurney (Escape Shaft 2)

View of the shaft excavation works and temporary reinforced concrete lining wall in progress at the Escape Shaft 2 site.