August 31, 2019
Pandangan udara tapak Stesen MRT Bandar Malaysia Selatan menunjukkan penggalian kekotak stesen dan kerja-kerja sengkang sedang dijalankan.

Sungai Besi Air Force Base (Bandar Malaysia South)

Aerial view of the Bandar Malaysia South site showing station box excavation and strutting works in progress.
August 31, 2019
Pandangan udara tapak Portal Selatan menunjukkan kerja-kerja gali dan timbus sengkang sementara dan penggalian sedang dijalankan.

South Portal

Aerial view of the South Portal site showing the cut and cover temporary strutting and excavation works in progress.
August 15, 2019
Pandangan udara Syaf Kecemasan 1 menunjukkan kerja-kerja pembinaan asas kren 200 tan dan 600 tan untuk pengambilan semula mesin pengorek terowong.

Jalan Sultan Azlan Shah (Escape Shaft 1, North Portal)

Aerial view of Escape Shaft 1 showing the construction works of 200 ton and 600 ton crane foundation for tunnel boring machine retrieval.
July 31, 2019
Pandangan Syaf Kecemasan 1 menunjukkan aras bilik loji dengan pembukaan sementara untuk pengambilan semula mesin pengorek terowong.

Jalan Sultan Azlan Shah (Escape Shaft 1, North Portal)

View of Escape Shaft 1 showing the plantroom level with temporary opening for Tunnel Boring Machine retrieval.
July 31, 2019
Pandangan keseluruhan Pintu Masuk C Stesen MRT Sentul Barat.

Jalan Sultan Azlan Shah (Sentul West)

Overall view of Entrance C of the Sentul West MRT Station.
July 31, 2019
Pandangan udara penyediaan kren gantri di tapak Stesen MRT Titiwangsa.

Jalan Tun Razak (Titiwangsa)

Aerial view of the gantry crane setup at the Titiwangsa MRT Station site.
July 31, 2019
Pandangan kerja-kerja pembinaan untuk konkrit bertetulang papak bumbung Pintu Masuk C Stesen MRT Hospital Kuala Lumpur.

Jalan Tun Razak (Hospital Kuala Lumpur)

View of the construction works for reinforced concrete at Hospital Kuala Lumpur MRT Station Entrance C roof slab.
July 31, 2019
Pandangan bahagian terowong yang telah siap dari Persilangan Hospital Kuala Lumpur ke Stesen MRT Ampang Park dengan landasan lokomotif sementara untuk membersihkan tanah di Syaf Penyelenggaraan 1.

Jalan Tun Razak (Intervention Shaft 1)

View of the completed tunnel section from Hospital Kuala Lumpur Crossover to Ampang Park MRT Station with temporary loco track for earth mucking at the Intervention Shaft 1.
July 31, 2019
Pandangan udara tapak Stesen MRT Kampung Baru Utara menunjukkan papak bumbung dan kerja-kerja ruang legar sedang dibina.

Jalan Raja Muda Abdul Aziz (Kampung Baru North)

Aerial view of Kampung Baru North MRT Station site showing the roof slab and concourse works in construction.