December 31, 2019
Penyingkiran kerja acuan dinding tetulang sedang dijalankan di tapak Stesen MRT Bandar Malaysia Selatan.

Sungai Besi Air Force Base (Bandar Malaysia Selatan)

Reinforced wall formwork removal in progress at the Bandar Malaysia Selatan MRT Station site.
December 31, 2019
Pandangan udara tapak Portal Selatan menunjukkan kerja-kerja penggalian yang sedang dijalankan.

South Portal

Aerial view of the South Portal site showing the ongoing excavation works
December 3, 2019
Pandangan keseluruhan tapak Syaf Kecemasan 2 yang sudah siap 52%.

Jalan Gurney (Escape Shaft 2)

Overall view of the Escape Shaft 2 site which is 52% completed.
November 30, 2019
Pandangan udara Stesen MRT Sentul Barat.

Jalan Sultan Azlan Shah (Sentul Barat)

Aerial view of the Sentul Barat MRT Station.
November 30, 2019
Pandangan pembinaan pengukuhan di aras ruang legar Stesen MRT Raja Uda.

Jalan Raja Muda Abdul Aziz (Raja Uda)

View of the erection of reinforcement at Raja Uda MRT Station concourse level.
November 30, 2019
Pandangan pembinaan struktur bukan galas beban konkrit tetulang di aras ruang legar bawah Stesen MRT Ampang Park.

Jalan Tun Razak (Ampang Park)

Pandangan pembinaan struktur bukan galas beban konkrit tetulang di aras ruang legar bawah Stesen MRT Ampang Park.
November 30, 2019
Pandangan keseluruhan tapak Stesen MRT Persiaran KLCC

Jalan Binjai (Persiaran KLCC)

Overall view of the Persiaran KLCC MRT Station site.
November 30, 2019
Pandangan udara tapak Stesen MRT Chan Sow Lin menunjukkan pembinaan Lebuhraya DUKE.

Jalan Chan Sow Lin (Chan Sow Lin)

Aerial view of the Chan Sow Lin MRT Station site showing the construction of DUKE highway.
November 30, 2019
Pembuangan acuan untuk dinding luaran dan tuangan pertama di aras bawah Syaf Penyelenggaraan 3.

Jalan Chan Sow Lin (Intervention Shaft 3)

Removal of formwork for external wall and first casting at the Intervention Shaft 3 lower level.