June 30, 2022
Kemasan yang telah siap di aras ruang legar dan platform Stesen MRT Raja Uda.

Jalan Raja Muda Abdul Aziz (Raja Uda)

Completed finishes at the concourse and platform levels of the Raja Uda MRT Station.
June 30, 2022
Pandangan bangunan Syaf Kecemasan 2 dari aras tanah.

Jalan Gurney (Escape Shaft 2)

View of the Escape Shaft 2 building from ground level.
June 30, 2022
Kemasan seni bina untuk aras platform bawah Stesen MRT Ampang Park.

Jalan Tun Razak (Ampang Park)

Architectural finishes for the Ampang Park MRT Station.lower platform level.
June 30, 2022
Kerja-kerja pemasangan salutan untuk Pintu Masuk B, kawasan tidak berbayar di aras ruang legar Stesen MRT Persiaran KLCC.

Jalan Binjai (Persiaran KLCC)

Cladding installation for Entrance B, unpaid area at the concourse level of the Persiaran KLCC MRT Station.
June 30, 2022
Kerja-kerja penyalutan sedang dijalankan di aras ruang legar Stesen MRT Conlay.

Jalan Conlay (Conlay)

Ongoing cladding works at Conlay MRT Station concourse level
June 30, 2022
Kerja-kerja pemasangan perkhidmatan telah siap di dalam bilik tangki air Syaf Penyelenggaraan 2.

Kampung Pandan Roundabout (Intervention Shaft 2)

Completed services installation in Intervention Shaft 2 water tank room.
June 30, 2022
Pemasangan perkhidmatan telah siap di Bilik Kawalan Api Syaf Kecemasan 3.

Jalan Peel (Escape Shaft 3)

Completed services installation in Escape Shaft 3 Fire Control Room.
June 30, 2022
Kerja-kerja sivil luaran, landskap dan pembinaan saliran dalaman sedang dijalankan di Syaf Penyelenggaraan 3 sepanjang Jalan Chan Sow Lin.

Jalan Chan Sow Lin (Intervention Shaft 3)

External civil works, landscaping and internal drainage construction works in progress at the Intervention Shaft 3.
June 30, 2022
Pembinaan papak apron di parameter bangunan pintu masuk Stesen MRT Bandar Malaysia Utara.

Sungai Besi Air Force Base (Bandar Malaysia Utara)

Construction of apron slab at Bandar Malaysia Utara MRT Station entrance parameter building.