September 30, 2022
Pintu Kutipan Tambang Automatik di aras ruang legar Stesen MRT Conlay.

Jalan Conlay (Conlay)

The Automatic Fare Collection gate at the Conlay MRT Station concourse level.
September 30, 2022
Pandangan luaran Syaf Kecemasan 3 menunjukkan 100% penyiapan dan sedia untuk pra-Pemeriksaan Cermat Akhir

Jalan Peel (Escape Shaft 3)

External view of the Escape Shaft 3 showing 100% completion and ready for pre-Pemeriksaan Cermat Akhir inspection.
September 30, 2022
Pandangan udara Portal Selatan.

South Portal

Aerial view of the South Portal.
September 30, 2022
Bangku platform telah dipasang di aras platform Stesen MRT Chan Sow Lin.

Jalan Chan Sow Lin (Chan Sow Lin)

Platform benches installed at the Chan Sow Lin MRT Station platform level.
September 30, 2022
Syaf Penyelenggaraan 3 telah siap sepenuhnya

Jalan Chan Sow Lin (Intervention Shaft 3)

Intervention Shaft 3 fully completed
September 30, 2022
Kesediaan Bilik Penyedut Asap di Stesen MRT Bandar Malaysia Utara.

Sungai Besi Air Force Base (Bandar Malaysia Utara)

Readiness of the Smoke Extraction Fan Room at the Bandar Malaysia Utara MRT Station.
September 30, 2022
Kerja-kerja pembinaan papak apron sedang dijalankan di Pintu Masuk B Stesen MRT Bandar Malaysia Selatan

Sungai Besi Air Force Base (Bandar Malaysia Selatan)

Apron slab construction works in progress at the Bandar Malaysia Selatan MRT Station Entrance B.
September 30, 2022
Kerja-kerja pengukuhan bagi Pemeriksaan Cermat Akhir di Portal Selatan.

South Portal

Rectification works for Pemeriksaan Cermat Akhir inspection at the South Portal.
September 29, 2022
Pengujian dan pentauliahan sistem pintu Kutipan Tambang Automatik sedang dijalankan di Stesen MRT Taman Naga Emas.

Taman Naga Emas

Testing and commissioning of Automatic Fare Collection gate system in progress at the Taman Naga Emas MRT Station.