SLIP ROAD CLOSURE AT JALAN JIM QUEE, JOHOR BAHRU (NEAR HOTEL ZAMBURGER GRAND JADE, STULANG LAUT-BOUND)
2024
2024
Activity Time
24 hours
Description
Please be informed that slip road closure will be implemented at Jalan Jim Quee, Johor Bahru (near Hotel Zamburger Grand Jade, Stulang Laut-bound) from 26 July 2024 until 31 August 2024. The works will be carried out 24 hours a day for 37 days.
Activity
To facilitate trestle erection works, segmental box girder launching works and other RTS Link project-related works
CONTRA FLOW ACTIVATION ON JALAN JIM QUEE 2, JOHOR BAHRU (NEAR BANGUNAN SULTAN ISKANDAR)
2024
2024
Activity Time
1.00 AM - 3.00 AM
Description
Please be informed that there will be a contra flow activation on Jalan Jim Quee 2, Johor Bahru (near Bangunan
Sultan Iskandar) from 14 July 2024 to 25 July 2024 (excluding Friday, Saturday and Sunday). The works will be
carried out from 1:00am to 3:00am, for 9 days.
Activity
To facilitate the U-shell beams delivery and other RTS Link project-related works
CONTINUATION OF LEFT LANE CLOSURE AT JALAN TUN ABDUL RAZAK, JOHOR BAHRU (CITY CENTRE–BOUND)
2024
2024
Activity Time
24 hours
Description
To facilitate U-shell beam launching works, Bukit Chagar station construction works and other RTS Link project-related works
Activity
To facilitate U-shell beam launching works, Bukit Chagar station construction works and other RTS Link project-related works
CONTINUATION OF FULL LANE CLOSURE AT JALAN TEBRAU HEADING TOWARDS JALAN TUN ABDUL RAZAK (CITY CENTRE– BOUND), JOHOR BAHRU
2024
2024
Activity Time
24 hours
Description
Please be informed there will be a continuation of partial road closure at Jalan Tebrau heading towards Jalan Tun Abdul Razak (City Centre–bound) will be continue from 28 June 2024 until 30 September 2024. The construction works will be carried out 24 hours for 94 days.
Activity
To facilitate the station construction works and other RTS Link Project-related works
PARTIAL ROAD CLOSURE BY STAGES AT JALAN IBRAHIM SULTAN, JOHOR BAHRU (NEAR HARLEY DAVIDSON, BOTH BOUND)
2024
2024
Activity Time
9.00 PM - 5.00 AM
Description
Please be informed that partial road closure by stages will be conducted at Jalan Ibrahim Sultan, Johor Bahru (near Harley Davidson, both bound) from 5 June 2024 until 31 July 2024. The works will be carried out from 9:00 pm until 5:00 am for 57 days.
Activity
To facilitate segmental box girder (SBG) launching works and other RTS Link project-related works
INTERMITTENT LANES CLOSURE BY STAGES AT KM1.0 – KM0.8 JOHOR CAUSEWAY (WOODLANDS, SINGAPORE-BOUND)
2024
2024
Activity Time
8.00 AM - 3.00 PM
Description
Please be informed that an intermittent lanes closure by stages will be implemented at Johor Causeway (Woodlands, Singapore-bound) from 10 June 2024 until 10 July 2024. The works will be carried out from 8:00 p.m. until 3:00 a.m. for 31 days.
Activity
To facilitate segmental box girder (SBG) launching works and other RTS Link project-related works.
PARTIAL ROAD CLOSURE AT JALAN JIM QUEE, JOHOR BAHRU (NEAR TRAFFIC LIGHT JUNCTION, JALAN ISMAIL SULTAN-BOUND)
2024
2024
Activity Time
9.00 PM - 5.00 AM
Description
Please be informed that partial road closure will be implemented at Jalan Jim Quee, Johor Bahru (near traffic light junction, Jalan Ismail Sultan-bound) from 11 June 2024 until 31 July 2024. The works will be carried out from 9:00 pm until 5:00 am (depending on the traffic flow) for 50 days.
Activity
To facilitate segmental box girder (SBG) launching works and other RTS Link project-related works.
PARTIAL ROAD CLOSURE OF JALAN ISMAIL SULTAN, JOHOR BAHRU (NEAR GRAND BLUE WAVE (GBW) HOTEL, BOTH BOUND)
2024
2024
Activity Time
9:00 p.m. – 5:00 a.m.
Description
Please be informed that partial road closure of Jalan Ismail Sultan, Johor Bahru (near Grand Blue Wave (GBW) Hotel) will be conducted from 27 May 2024 until 31 July 2024.
Activity
To facilitate U-beam & segmental box girder (SBG) launching works and other RTS Link project-related works.
INTERMITTENT LANE CLOSURE BY STAGES AT JOHOR CAUSEWAY (BOTH BOUND)
2024
2024
Activity Time
10:00 p.m. – 5:00 a.m.
Description
Please be informed that an intermittent lane closure by stages will be implemented at Johor Causeway (both bound) from 19 May 2024 until 5 June 2024.
Activity
To facilitate bracket installation, bracket dismantling and other RTS Link project - related works