Traffic Announcement
LONG TERM INTERMITTENT PARTIAL LANE CLOSURES ALONG JALAN SULTAN AZLAN SHAH (Sunny Point – JPJ Batu Uban)
2025
2026
Activity Time
8.00 am – 4.00 pm
Description
Please be informed that long-term intermittent partial lane closures along a stretch of Jalan Sultan Azlan Shah (towards Komtar) will be implemented from 27 October 2025 to 26 January 2026. The closure will be implemented from 8:00 am to 4:00 pm daily for a duration of 91 days.
Activity
Relocation Of Drainage And Road Widening Works
SHORT-TERM INTERMITTENT PARTIAL LANE CLOSURES ON TUN DR. LIM CHONG EU HIGHWAY
2025
2025
Activity Time
9.00 am – 5.00 pm
Description
Please be informed that short-term intermittent partial lane closures along a stretch of Jalan Sultan Azlan Shah will be implemented from 27 Oktober 2025 until 14 November 2025 the closure will be implemented between 9:00 am and 5:00 pm for a duration of 18 days.
Activity
Tree cutting and road widening
SHORT-TERM INTERMITTENT LANE CLOSURE ALONG A STRETCH OF JALAN TENGAH.
2025
2025
Activity Time
10.00 pm – 5.00 am
Description
Please be informed that short-term partial lane closures along a stretch of Jalan Tengah, will be implemented from 24 October 2025 to 21 November 2025. The closures will be carried out between 10:00 pm and 5:00 am.
Activity
Utilities Piloting and Utilities Relocation
PARTIAL NIGHT LANE CLOSURE ON JALAN TENGAH BETWEEN THE INTERSECTIONS OF PERSIARAN MAHSURI AND JALAN MAYANG PASIR.
2025
2025
Activity Time
10.00 pm to 5.00 am
Description
Please be informed that a partial night lane closure will be implemented on Jalan Tengah, near Pantai Hospital Pulau Pinang and Sekolah Menengah Kebangsaan Raja Tun Uda, from 16 October 2025 to 9 November 2025. This activity will take place from 10:00 PM to 5:00 AM.
Activity
Piloting & utility relocation works.
LONG TERM INTERMITTENT PARTIAL LANE CLOSURES ALONG JALAN TUN DR AWANG
2025
2026
Activity Time
8.00 am – 4.00 pm
Description
Please be informed that long-term intermittent partial lane closures along a stretch of Jalan Tun Dr Awang (towards Bayan Lepas) will be implemented from 25 October 2025 to 23 January 2026. The closure will be implemented from 8:00 am to 4:00 pm daily for a duration of 90 days.
Activity
Tree cutting, drainage relocation and road widening.
SHORT-TERM INTERMITTENT PARTIAL LANE CLOSURE ALONG JALAN SULTAN AZLAN SHAH
2025
2025
Activity Time
10.00 PM to 5.00 AM
Description
Please be informed that short-term partial lane closures on the left most lanes on both directions along Jalan Sultan Azlan Shah and a stretch of Jalan Mayang Pasir will be implemented from 24 October 2025 to 21 November 2025. The closures will be carried out between 10:00 pm and 5:00 am.
Activity
Utilities Piloting
PARTIAL NIGHT LANE CLOSURE ON JALAN SULTAN AZLAN SHAH BETWEEN THE JALAN TENGAH APARTMENT AND PENANG SNAKE TEMPLE
2025
2025
Activity Time
10.00 PM to 5.00 AM
Description
Please be informed that a partial night lane closure will be implemented on Jalan Sultan Azlan Shah, between the Jalan Tengah Apartment and Penang Snake Temple from 24 October 2025 to 21 November 2025.
Activity
Utilities Piloting
SHORT-TERM PARTIAL INTERMITTENT LANE CLOSURE ALONG A STRETCH OF JALAN SULTAN AZLAN SHAH
2025
2025
Activity Time
10.00 pm – 5.00 am
Description
Please be informed that short-term partial lane closures along a stretch of Jalan Sultan Azlan Shah, will be implemented from 24 October 2025 to 21 November 2025. The closures will be carried out between 10:00 pm and 5:00 am.
Activity
Utilities Piloting
SHORT-TERM INTERMITTENT LANE CLOSURE ALONG A STRETCH OF JALAN TENGAH.
2025
2025
Activity Time
10.00 pm – 5.00 am
Description
Please be informed that short-term partial lane closures along a stretch of Jalan Sultan Azlan Shah, will be implemented from 24 October 2025 to 21 November 2025. The closures will be carried out between 10:00 pm and 5:00 am.
Activity
Utilities Piloting