Traffic Announcement
LEFT LANE CLOSURE AT JALAN TUN ABDUL RAZAK (NEAR JB SENTRAL, DANGA BAY BOUND), JOHOR BAHRU
2025
2026
Activity Time
24 Hours
Description
Please be informed that there will be left lane closure at Jalan Tun Abdul Razak (near JB Sentral, Danga Bay bound), Johor Bahru from 09 June 2025 to 1 February 2026. The works will be carried out 24 hours daily for seven (7) months and twenty-three (23) days.
Activity
To facilitate the machine mobilization works, installation of deck slab and roofing works and other RTS Link project-related works.
FULL LINK ROAD CLOSURE AT JOHOR BAHRU DISTRICT (JOHOR BAHRU-ENDAU ROAD, SECTION 0.10 TO SECTION 0.20)
2025
2026
Activity Time
24 hours
Description
Please be informed that there will be a full link road closure, Jalan Johor Bahru-Endau from Section 0.10 to Seksyen 0.20) from 03 June 2025 to 31 December 2026. The construction works will be carried out for 24 hours a day, for eighteen (18) months and twenty eight (28) days.
Activity
To facilitate the construction of bore pile works, pile cap works, pier column works and any other related works to the RTS Link project.
CONTINUATION OF INTERMITTENT PARTIAL LANE CLOSURE BY STAGES IN THE CITY CENTRE, JOHOR BAHRU
2025
2025
Activity Time
10:00 p.m - 5:00 a.m | 9:00 a.m - 5:00 p.m
Description
Please be informed that continuation intermittent partial lane closure by stages will be implemented on Jalan Trus, Jalan Abdullah Ibrahim, Jalan Md Noor, Jalan Gereja, Jalan Ngee Heng and Jalan Abdul Rahman Andak, Johor Bahru from 27 May 2025 to 20 October 2025. The works will be carried out from 10:00p.m to 5:00.am and 9:00a.m to 5:00p.m, for a period of four (4) months and twenty-four (24) days.
Activity
To facilitate the machine mobilization works, utilities detection & relocation works and other RTS Link project-related works.
CONTINUATION OF FULL BOUND CLOSURE AND ACTIVATION OF CONTRA FLOW AT JALAN TEBRAU, JOHOR BAHRU (SKUDAI/SENAI BOUND)
2025
2025
Activity Time
11:00 p.m – 5:30 a.m
Description
Please be informed that there will be a continuation of full bound closure and activation of contra flow at Jalan Tebrau, Johor Bahru (Skudai/Senai bound) from 20 May 2025 to 21 May 2025. The works will be carried out from 11:00 p.m to 5:30 a.m for two (2) days.
Activity
To facilitate the machine mobilization works, concreting works and other RTS Link project-related works.
FULL BOUND CLOSURE AND ACTIVATION OF CONTRA FLOW AT JALAN TEBRAU, JOHOR BAHRU (SKUDAI/SENAI BOUND)
2025
2025
Activity Time
10:00 p.m – 5:00 a.m
Description
Please be informed that there will be a full bound closure and activation of contra flow at Jalan Tebrau, Johor Bahru (Skudai/Senai bound) from 13 May 2025 to 14 May 2025. The works will be carried out from 10:00 p.m to 5:00 a.m for two (2) days.
Activity
To facilitate the machine mobilization works, cantilever bracket adjustment, concreting works and other RTS Link project-related works.
INTERMITTENT LANE CLOSURE BY STAGES AT KM0.75 JOHOR CAUSEWAY (BOTH BOUND)
2025
2025
Activity Time
8:00 p.m. – 3:00 a.m. (Woodlands, Singapore-bound) | 10.00 p.m. – 5.00 a.m. (Johor Bahru, Malaysia-bound)
Description
Please be informed that an intermittent lane closure by stages will be implemented at KM0.75 Johor Causeway (both-bound) from 5 May 2025 until 9 May 2025. The works will be carried out from 8:00 p.m. until 3:00 a.m. (Woodlands, Singapore-bound) and from 10:00 p.m. until 5:00 a.m. (Johor Bahrubound) for 5 days.
Activity
To facilitate concrete barrier reinstatement work.
INTERMITTENT ROAD CLOSURE AT JALAN TUN ABDUL RAZAK, JOHOR BAHRU (NEAR MENARA JLAND & KOMTAR JBCC, CITY CENTRE BOUND)
2025
2025
Activity Time
11:00 p.m. - 6:00 a.m.
Description
Please be informed that an intermittent road closure at Jalan Tun Abdul Razak (near Menara Jland & Komtar JBCC) will be implemented from 1 May 2025 until 31 May 2025. The construction works will be carried out from 11:00 p.m. to 6:00 a.m. for 31 days.
Activity
To facilitate segmental box girder painting works, road premix works and other RTS Link project-related works.
INTERMITTENT ROAD CLOSURE AT JALAN TUN ABDUL RAZAK, JOHOR BAHRU (SKUDAI/SENAI AND DANGA BAY BOUND)
2025
2025
Activity Time
10:00 p.m – 5:00 a.m
Description
Please be informed that an intermittent road closure at Jalan Tun Abdul Razak, Johor Bahru will be implemented from 18 January 2025 to 26 January 2025. The works will be carried out from 10:00 p.m to 5:00 a.m for nine (9) days.
Activity
To facilitate the machine mobilization works, utilities relocation works, U-beam & Tbeam launching works and other RTS Link project-related works.
RIGHT LANE CLOSURE AT JALAN TUN ABDUL RAZAK, JOHOR BAHRU (NEAR JOHOR TOWER HARN LEN, SKUDAI/SENAI-BOUND)
2024
2026
Activity Time
24 hours
Description
Please be informed that a right lane closure will be implemented at Jalan Tun Abdul Razak, Johor Bahru (Skudai/Senai-bound) from 13 November 2024 to 13 December 2024. The construction works will be carried out for 24 hours daily, for 17 month 11 days.
Activity
To facilitate piling works, pier works, external ramp construction works and other RTS Link project-related works.