INTERMITTENT FULL ROAD CLOSURE ALONG JALAN GEREJA, JALAN NGEE HENG AND JALAN TRUS, JOHOR BAHRU
15 Oct
2025
30 Oct
2025

Activity Time
10.00 PM - 5.30 AM

Description

Please be informed that an intermittent full road closure at Jalan Gereja, Jalan Ngee Heng and Jalan Trus will be implemented from 15 October 2025 to 30 October 2025. The works will be carried out from 10.00 PM to 5.30 AM, for a duration of two (2) weeks.

Activity

To facilitate machine mobilization works, launching works and other RTS Link project related works.


SHORT-TERM PARTIAL LANE CLOSURE ON INNER ROAD NEAR GIANT BAYAN BARU (JALAN TENGAH)
13 Oct
2025
23 Oct
2025

Activity Time
10 PM - 5 AM

Description

Short-term partial lane closures at inner road in front Giant Bayan Baru will be implemented from 13 October 2025 to 23 October 2025. The closures will be carried out between 10:00 pm to 5:00 am

Activity

To facilitate relocation of TNB 132kV cable for Penang LRT: Mutiara Line (PML) Project


TEMPORARY ROAD CLOSURE AT JALAN 2/90, TAMAN PERTAMA CHERAS
29 Sep
2025
31 Dec
2025

Activity Time
10 PM- 5 AM

Description

Fabrication, Supply, Deliver and Installation of Rain Splash Barrier System, Roof Access, Working Platform and Other Associated Works at MRT Taman Pertama Station

Activity

A temporary road closure will be implemented at Jalan 2/90, Taman Pertama, Cheras to facilitate construction works. This closure is scheduled to take place daily from 10.00 PM to 5.00 AM, from 29-09-2025 until 31-12-2025.


INTERMITTENT FULL ROAD CLOSURE AT JALAN TEBRAU (KOTA TINGGI-BOUND) AND JALAN TUN ABDUL RAZAK (SKUDAI/SENAI-BOUND), JOHOR BAHRU
29 Sep
2025
2 Oct
2025

Activity Time
10.00 PM - 5.30 AM

Description

Intermittent full road closures along Jalan Tebrau (Kota Tinggi-bound) and Jalan Tun Abdul Razak (Skudai/Senai-bound) will be implemented from 29 September 2025 to 2 October 2025. The works will be carried out from 10.00 PM to 5.30 AM for four (4) days.

Activity

To facilitate the machine mobilization works, launching works, dismantle guard rail & fencing works, demolished NJB/parapet Wall, concreting works and other RTS Link project-related works.


INTERMITTENT LANE CLOSURES BY STAGES AT KM0.75 JOHOR CAUSEWAY (BOTH BOUNDS)
22 Sep
2025
3 Oct
2025

Activity Time
8.00 PM - 3.00 AM (Woodlands, Singapore-bound) 10.00 PM - 5.00 AM (Johor Bahru, Malaysia-bound)

Description

Intermittent lane road closure at KM 0.75 Johor Causeway will be implemented from 22 September 2025 to 3 October 2025. The works will be carried out from 8.00 PM to 3.00 AM (Woodlands, Singapore-bound) and from 10.00 PM to 5.00 AM (Johor Bahru, Malaysia-bound), for a duration of twelve (12) days.

Activity

To facilitate concrete barrier rectification works, street lighting sticker installation, reflective sticker installation and other RTS Link project-related works.


LONG-TERM PARTIAL LANE CLOSURES ALONG JALAN SULTAN AZLAN SHAH (BOTH DIRECTIONS) (SUNGAI TIRAM)
22 Sep
2025
31 Dec
2025

Activity Time
24 Hours

Description

The long-term partial lane closures on both directions along Jalan Sultan Azlan Shah, near the Sungai Tiram area, will be implemented from 22 September 2025 to 31 December 2025. The closures will be carried out for 24 hours a day over a period of three (3) months and ten (10) days. During the implementation of the lane closures, the fast lanes in both directions, along the stretch between Penang International Airport and the Jalan Mayang Pasir Traffic Light Junction will be affected.

Activity

To facilitate preliminary works for the LRT Penang: Mutiara Line (PML) project, including tree cutting, soil investigation and utility relocation.


INTERMITTENT FULL ROAD CLOSURE ALONG JALAN GEREJA, JOHOR BAHRU
22 Sep
2025
10 Oct
2025

Activity Time
10.00 PM - 5.30 AM

Description

Please be informed that an intermittent full road closure along Jalan Gereja will be implemented from 22 September 2025 to 10 October 2025. The works will be carried out from 10.00 PM to 5.30 AM, for a duration of eighteen (18) days.

Activity

To facilitate machine mobilization works, concreting works and other RTS Link projectrelated works.


CONTINUATION OF INTERMITTENT LEFT LANE CLOSURE AT JALAN TUN ABDUL RAZAK, JOHOR BAHRU (CITY CENTRE-BOUND)
18 Sep
2025
18 Oct
2025

Activity Time
10.00 PM - 5.30 AM

Description

Please be informed that an intermittent left lane closure on Jalan Tun Abdul Razak, Johor Bahru (City Centrebound) will be extended from 18 September 2025 until 18 October 2025. The construction works will be carried out from 10.00 PM to 5.30 AM, for a duration of one (1) month.

Activity

To facilitate machine mobilization, crosshead portal work related, installation of formwork, concreting works, launching works and other RTS Link project-related works.


ROAD REALIGNMENT ALONG JALAN TUN ABDUL RAZAK, JOHOR BAHRU (CITY CENTRE-BOUND)
12 Sep
2025
12 Jan
2026

Activity Time
24 hours

Description

Please be informed that the road realignment at Jalan Tun Abdul Razak, Johor Bahru (City Centre-bound) will be implemented from 12 September 2025 until 12 January 2026. The road realignment will be carried out for 24 hours a day over a period of four (4) months.

Activity

To facilitate machine mobilisation, pile cap works, pier column works and other RTS Link project-related works.