Traffic Announcement
CONTINUATION OF INTERMITTENT PARTIAL LANE CLOSURE BY STAGES IN THE CITY CENTRE, JOHOR BAHRU
2025
2025
Activity Time
10:00 p.m - 5:00 a.m | 9:00 a.m - 5:00 p.m
Description
Please be informed that continuation intermittent partial lane closure by stages will be implemented on Jalan Trus, Jalan Abdullah Ibrahim, Jalan Md Noor, Jalan Gereja, Jalan Ngee Heng and Jalan Abdul Rahman Andak, Johor Bahru from 27 May 2025 to 20 October 2025. The works will be carried out from 10:00p.m to 5:00.am and 9:00a.m to 5:00p.m, for a period of four (4) months and twenty-four (24) days.
Activity
To facilitate the machine mobilization works, utilities detection & relocation works and other RTS Link project-related works.
CONTINUATION OF FULL BOUND CLOSURE AND ACTIVATION OF CONTRA FLOW AT JALAN TEBRAU, JOHOR BAHRU (SKUDAI/SENAI BOUND)
2025
2025
Activity Time
11:00 p.m – 5:30 a.m
Description
Please be informed that there will be a continuation of full bound closure and activation of contra flow at Jalan Tebrau, Johor Bahru (Skudai/Senai bound) from 20 May 2025 to 21 May 2025. The works will be carried out from 11:00 p.m to 5:30 a.m for two (2) days.
Activity
To facilitate the machine mobilization works, concreting works and other RTS Link project-related works.
FULL BOUND CLOSURE AND ACTIVATION OF CONTRA FLOW AT JALAN TEBRAU, JOHOR BAHRU (SKUDAI/SENAI BOUND)
2025
2025
Activity Time
10:00 p.m – 5:00 a.m
Description
Please be informed that there will be a full bound closure and activation of contra flow at Jalan Tebrau, Johor Bahru (Skudai/Senai bound) from 13 May 2025 to 14 May 2025. The works will be carried out from 10:00 p.m to 5:00 a.m for two (2) days.
Activity
To facilitate the machine mobilization works, cantilever bracket adjustment, concreting works and other RTS Link project-related works.
INTERMITTENT LANE CLOSURE BY STAGES AT KM0.75 JOHOR CAUSEWAY (BOTH BOUND)
2025
2025
Activity Time
8:00 p.m. – 3:00 a.m. (Woodlands, Singapore-bound) | 10.00 p.m. – 5.00 a.m. (Johor Bahru, Malaysia-bound)
Description
Please be informed that an intermittent lane closure by stages will be implemented at KM0.75 Johor Causeway (both-bound) from 5 May 2025 until 9 May 2025. The works will be carried out from 8:00 p.m. until 3:00 a.m. (Woodlands, Singapore-bound) and from 10:00 p.m. until 5:00 a.m. (Johor Bahrubound) for 5 days.
Activity
To facilitate concrete barrier reinstatement work.
INTERMITTENT ROAD CLOSURE AT JALAN TUN ABDUL RAZAK, JOHOR BAHRU (NEAR MENARA JLAND & KOMTAR JBCC, CITY CENTRE BOUND)
2025
2025
Activity Time
11:00 p.m. - 6:00 a.m.
Description
Please be informed that an intermittent road closure at Jalan Tun Abdul Razak (near Menara Jland & Komtar JBCC) will be implemented from 1 May 2025 until 31 May 2025. The construction works will be carried out from 11:00 p.m. to 6:00 a.m. for 31 days.
Activity
To facilitate segmental box girder painting works, road premix works and other RTS Link project-related works.
INTERMITTENT ROAD CLOSURE AT JALAN TUN ABDUL RAZAK, JOHOR BAHRU (SKUDAI/SENAI AND DANGA BAY BOUND)
2025
2025
Activity Time
10:00 p.m – 5:00 a.m
Description
Please be informed that an intermittent road closure at Jalan Tun Abdul Razak, Johor Bahru will be implemented from 18 January 2025 to 26 January 2025. The works will be carried out from 10:00 p.m to 5:00 a.m for nine (9) days.
Activity
To facilitate the machine mobilization works, utilities relocation works, U-beam & Tbeam launching works and other RTS Link project-related works.
RIGHT LANE CLOSURE AT JALAN TUN ABDUL RAZAK, JOHOR BAHRU (NEAR JOHOR TOWER HARN LEN, SKUDAI/SENAI-BOUND)
2024
2026
Activity Time
24 hours
Description
Please be informed that a right lane closure will be implemented at Jalan Tun Abdul Razak, Johor Bahru (Skudai/Senai-bound) from 13 November 2024 to 13 December 2024. The construction works will be carried out for 24 hours daily, for 17 month 11 days.
Activity
To facilitate piling works, pier works, external ramp construction works and other RTS Link project-related works.
INTERMITTENT ROAD CLOSURE AT JALAN TUN ABDUL RAZAK, JOHOR BAHRU (NEAR MERLIN TOWER, DANGA BAY-BOUND)
2024
2024
Activity Time
11:00 p.m. – 6:00 a.m.
Description
Please be informed that an intermittent road closure at Jalan Tun Abdul Razak, Johor Bahru (near Merlin Tower, Danga Bay-bound) will be implemented from 15 November 2024 until 30 November 2024. The construction works will be carried out from 11:00 p.m. until 6:00 a.m. for 16 days.
Activity
To facilitate launching girder dismantling works and RTS Link project-related works.
INTERMITTENT LANE CLOSURE BY STAGES AT KM1.0 – KM0.7, JOHOR CAUSEWAY (BOTH-BOUNDS)
2024
2024
Activity Time
8:00 p.m. – 5:00 a.m. (Stage 1) 8:00 p.m. – 3.00 a.m. (Stage 2 and 3) 10:00 p.m. – 5:00 a.m. (Stage 4 and 5)
Description
Please be informed that there will be an intermittent lane closure by stages at Johor Causeway (both bounds) from 4 November 2024 until 08 November and from 15 November 2024 until (including Saturday and Sunday). The works will be carried out from 8:00 p.m. until 3:00 a.m. (Stage 1), 8:00 p.m. until 5:00 a.m. (Stage 2) and 10:00 p.m. until 5:00 a.m. (Stage 3 and 4) for 20 days.
Activity
To facilitate parapet wall installation works, street lighting installation and other RTS Link project-related works.