PublicTraffic Announcement

Traffic Announcement

PERSIARAN JATI, DUKE2 & MRR2 AT JALAN KUALA SELANGOR
1 Oct
2019
30 Nov
2019

Activity Time
10:00 pm - 6:00 am

Description

Intermittent lane closures by stages will continue along Persiaran Jati, DUKE2 and MRR2 at Jalan Kuala Selangor from 01 November 2019 until 30 November 2019. The construction works will start from 10:00 pm - 6:00 am, for 1 month.

Activity

To facilitate installation of frame structure for piers, segment lifter assembly works , installation of segmental box girder (SBG) and any other related works.


PERSIARAN APEC (PUCHONG BOUND)
1 Nov
2019
31 Dec
2019

Activity Time
9:00 pm – 6:00 am

Description

Intermittent full bound closure will continue along Persiaran APEC (Puchong-bound) from 01 November 2019 until 31 December 2019. Construction works will start from 9:00 pm – 6:00 am, for 2 months.

Activity

To facilitate segmental box girder (SBG) launching and any other related works.


PERSIARAN APEC (CYBERJAYA BOUND)
1 Nov
2019
12 Dec
2019

Activity Time
24 hours

Description

Full road closure and activation of contra-flow will continue along Persiaran APEC (Cyberjaya Bound) from 01 November 2019 to 12 December 2019. Construction works will be 24 hours, for 1 month and 12 days.

Activity

To facilitate segmental box girder (SBG) launching, installation of parapet and noise barrier and any other related works.


SUNGAI BESI HIGHWAY
1 Nov
2019
14 Nov
2019

Activity Time
11:00 pm – 5:00 am

Description

Intermittent full bound closure will start along Sungai Besi Highway from KM12.0 to KM12.4 (Sungai Besi-bound) from 01 November 2019 until 14 November 2019. Construction works will start from 11:00 pm – 5:00 am, for 14 days.

Activity

To facilitate installation of frame structure for piers, segment lifter assembly works , installation of segmental box girder (SBG) and any other related works.


JALAN KAMPUNG BATU (NEAR S.J.K (C) MUN CHOONG)
1 Nov
2019
14 Dec
2019

Activity Time
10:00pm – 5:00am

Description

Continuation of full road closure along Jalan Kampung Batu (near S.J.K (C) Mun Choong) towards KTM Taman Wahyu, Taman Mastiara & Taman Tasik Indah from 01 November 2019 until 13 December 2019. Construction works will start from 10:00pm – 5:00am, for 1 month 13 days

Activity

To facilitate parapet installation and any other related works.


BULATAN LUMBA KUDA
30 Oct
2019
7 Dec
2019

Activity Time
10:00 pm - 5:00 am

Description

Intermittent lane closure by stages and activation of contra flow at ramp to Bulatan Lumba Kuda from Kuala Lumpur towards Bukit Jalil highway will start from 30 October 2019 until 07 December 2019. Construction works will start from 10:00 pm - 5:00 am, for 39 days.

Activity

To facilitate segmental box girder (SBG) launching, parapet wall installation and any other related works


KL-SEREMBAN HIGHWAY
26 Oct
2019
14 Jan
2020

Activity Time
10:00 pm - 5:00 am

Description

Intermittent lane closure by stages will continue at KL-Seremban highway from 26 October 2019 until 14 January 2020. Construction works will start from 10:00 pm - 5:00 am, for 81 days.

Activity

To facilitate segmental box girder (SBG) launching and any other related works.


JALAN SUASA 2, PEKAN SUNGAI BESI
25 Oct
2019
14 Jan
2020

Activity Time
24 Hours

Description

Full lane closure will continue at Jalan Suasa 2, Pekan Sungai Besi from 25 October 2019 until 14 January 2020. Construction works will be 24 hours, for 82 days.

Activity

To facilitate excavation works, sewerage relocation and any other related works.


JALAN UTAMA, SERDANG RAYA
26 Oct
2019
1 Mar
2020

Activity Time
11:00 pm - 5:00 am

Description

Full lane closure (Serdang bound) and intermittent activation of contra flow at Jalan Utama, Serdang Raya will start from 26 October 2019 until 29 February 2020. Construction works will start from 11:00 pm - 5:00 am, for 4 months.

Activity

To facilitate segmental box girder (SBG) launching, parapet wall installation and any other related works.