ProjectsTraffic Announcement

Traffic Announcement

SHORT-TERM INTERMITTENT PARTIAL LANE CLOSURE AT GAT JALAN MAGAZINE
13 Jun
2026
30 Jun
2026

Activity Time
10.00AM – 4.00PM

Description

Please be informed that a short-term periodic closure of the pedestrian walkway at Gat Jalan Magazine will be implemented from 13 June 2026 to 30 June 2026, between 10:00 AM and 4:00 PM, over a period of 18 days.

Activity

TREE CUTTING WORKS


LONG TERM INTERMITTENT PARTIAL LANE CLOSURES ALONG JALAN TUN DR AWANG (OPPOSITE CAWAN KUEY & SAJIAN – FUTSAL COURT)
20 Jun
2026
30 Aug
2026

Activity Time
8.00AM – 4.00PM

Description

Please be informed that a long-term periodic partial lane closure on Jalan Tun Dr. Awang will be implemented from 20 June to 30 August 2026, between 8:00 AM and 4:00 PM, over a period of 72 days.

Activity

ROAD WIDENING WORK


LONG-TERM INTERMITTENT PARTIAL LANE CLOSURES ALONG JALAN SULTAN AZLAN SHAH (SUNNY POINT JUNCTION – USM FIELD)
20 Jun
2026
5 Sep
2026

Activity Time
8.00AM – 4.00PM

Description

Please be informed that long-term intermittent partial lane closures along a stretch of Jalan Sultan Azlan Shah will be implemented from 20 June 2026 to 05 September 2026. The closure will be implemented from 8:00 am to 4:00 pm, over a period of 78 days.

Activity

RELOCATION OF DRAINAGE AND ROAD WIDENING WORKS


LONG-TERM INTERMITTENT PARTIAL LANE CLOSURE ALONG JALAN SULTAN AZLAN SHAH
17 Jun
2026
16 Aug
2026

Activity Time
10.00PM – 5.00AM

Description

Please be informed that a periodic partial lane closures along Jalan Sultan Azlan Shah will be implemented from 17 June to 16 August 2026, from 10:00 PM to 5:00 AM daily, over a period of 61 days.

Activity

IDENTIFY AND RELOCATION UTILITIES


LONG-TERM INTERMITTENT PARTIAL LANE CLOSURE ALONG JALAN SULTAN AZLAN SHAH
19 Jun
2026
16 Aug
2026

Activity Time
10.00PM – 5.00AM

Description

Please be informed that a a long-term periodic partial lane closure on Jalan Sultan Azlan Shah will be implemented from 19 June to 16 August 2026, between 10:00 pm and 5:00 am daily, over a period of 59 days.

Activity

IDENTIFY AND RELOCATION UTILITIES


LONG-TERM LANE DIVERSION ON JALAN TENGAH
7 Jun
2026
31 Dec
2028

Activity Time
24 Hours

Description

Please be informed that the long-term diversion at Jalan Tengah (both directions) will be implemented from 7 June 2026 until 31 December 2028. The diversion will be in effect 24 hours daily.

Activity

BORED PILE, PILE AP, PIER AND STRUCTURE WORKS


LONG-TERM LANE DIVERSION ON JALAN LAPANGAN TERBANG ANTARABANGSA PULAU PINANG (IN FRONT OF MULTI-STOREY CAR PARK BUILDING)
11 Jun
2026
31 Dec
2027

Activity Time
24 Hours

Description

Please be informed that a long-term traffic diversion along Jalan Lapangan Terbang Antarabangsa Pulau Pinang will be implemented from 11 June 2026 until 31 December 2027.

Activity

BORED PILE WORKS FOR THE LRT MUTIARA LINE PROJECT


SHORT-TERM INTERMITTENT PARTIAL NIGHT LANE CLOSURE ALONG JALAN PERMATANG DAMAR LAUT.
1 Jun
2026
30 Jun
2026

Activity Time
10.00PM – 5.00AM

Description

Please be informed that short-term intermittent partial lane closure at night will be implemented along Jalan Permatang Damar Laut (both directions) from 1 June 2026 to 30 June 2026.The closure period will be between 10:00 pm and 5:00 am, over a period of 30 days.

Activity

PRELIMINARY UTILITY WORKS.


SHORT-TERM FULL ROAD CLOSURE ALONG JALAN MAGAZINE (KOMTAR)
12 Jun
2026
13 Jun
2026

Activity Time
24 Hours

Description

Please be informed that a full 24-hour closure along Jalan Magazine will be implemented from 12 June 2026 to 13 June 2026.

Activity

UTILITY RELOCATION (PBA)