LONG-TERM INTERMITTENT NIGHT CLOSURES ON JALAN TUN DR. AWANG (PERSIARAN BUKIT JAMBUL)
2026
2026
Activity Time
10.00PM – 5.00AM
Description
Please be informed that a long-term periodic partial lane closure along Jalan Tun Dr. Awang towards Persiaran Bukit Jambul will be implemented from 3 August 2026 to 31 October 2026. The closure will be implemented from 10:00 PM to 5:00 AM, over a period of 89 days.
Activity
IDENTIFY AND RELOCATION UTILITIES
LONG-TERM INTERMITTENT PARTIAL LANE CLOSURE ALONG JALAN TUN DR AWANG
2026
2026
Activity Time
10.00PM – 5.00AM
Description
Please be informed that long-term intermittent partial night lane closures along a stretch of Jalan Tun Dr. Awang will be implemented from 01 August 2026 to 30 September 2026. The closure will be implemented from 10:00 PM to 5:00 AM.
Activity
IDENTIFY AND RELOCATION UTILITIES
LONG-TERM INTERMITTENT NIGHT CLOSURES ON JALAN TUN DR AWANG
2026
2026
Activity Time
10.00PM – 5.00AM
Description
Please be informed that long-term intermittent partial night lane closures along a stretch of Jalan Tun Dr. Awang will be implemented from 01 August 2026 to 31 October 2026. The closure will be implemented from 10:00 PM to 5:00 AM, over a period of 91 days.
Activity
IDENTIFY AND RELOCATION UTILITIES
SHORT-TERM PARTIAL NIGHT-TIME LANE CLOSURE ALONG JALAN TUN DR. AWANG
2026
2026
Activity Time
10.00PM – 5.00AM
Description
Please be informed that long-term partial night lane closure on Jalan Tun Dr. Awang will be implemented from 13 July to 30 September 2026. The closure will be implemented from 10:00 PM to 5:00 AM daily, over a period of 20 days.
Activity
IDENTIFY AND RELOCATION UTILITIES
SHORT-TERM INTERMITTENT PARTIAL NIGHT LANE CLOSURE ALONG JALAN PERMATANG DAMAR LAUT
2026
2026
Activity Time
10.00PM – 5.00AM
Description
Please be informed that short-term intermittent partial night lane closure will be implemented along Jalan Permatang Damar Laut (both directions) from 28 July 2026 to 16 August 2026.The closure period will be between 10:00 pm and 5:00 am, over a period of 19 days. The traffic management plan is as follows:
Activity
PRELIMINARY UTILITY WORKS.
LONG-TERM INTERMITTENT PARTIAL NIGHT LANE CLOSURE ALONG TUN DR. LIM CHONG EU EXPRESSWAY
2026
2026
Activity Time
10.00PM – 5.00AM
Description
Please be informed that a long-term periodic partial lane closure on the Tun Dr. Lim Chong Eu Expressway will be implemented from 21 July to 30 September 2026, from 10:00 PM to 5:00 AM daily, over a period of 71 days. The Traffic Management Plan is as follows:
Activity
ROAD WIDENING WORKS
CONTINUATION OF LEFT LANE CLOSURE AT JALAN LINGKARAN DALAM, JOHOR BAHRU (NEAR SHELL PETROL STATION)
2026
2026
Activity Time
24 Hours
Description
Please be informed that the left lane closure at Jalan Lingkaran Dalam (near Shell petrol station), will be extended from 21 July 2026 to 30 August 2026. The construction works will be carried out 24 hours, for one (1) month and ten (10) days.
Activity
To facilitate machinery mobilization works, drainage works, Mill & Pave works, road marking works, and other RTS Link project-related works.
LONG TERM INTERMITTENT NIGHT-TIME CLOSURE OF THE EXIT ROAD IN FRONT OF MULTI-STOREY CAR PARK. (PENANG INTERNATIONAL AIRPORT)
2026
2026
Activity Time
9.00PM – 5.00AM
Description
Please be informed that a long-term intermittent partial night lane closure will be implemented on Jalan Lapangan Terbang Antarabangsa Pulau Pinang from 16 July 2026 until 17 October 2026. The activity will take place from 9:00 PM to 5:00 AM, over a period of 93 days.
Activity
CONSTRUCTION WORK FOR LRT RUNWAY
LONG-TERM INTERMITTENT PARTIAL NIGHT LANE CLOSURE ALONG TUN DR. LIM CHONG EU EXPRESSWAY
2026
2026
Activity Time
10.00AM – 4.00PM
Description
Please be informed that a long-term periodic partial lane closures along Tun Dr. Lim Chong Eu Expressway will be implemented from 12 July to 30 September 2026, from 10:00 AM to 4:00 PM daily, over a period of 80 days.
Activity
TREE CUTTING WORKS