LONG-TERM INTERMITTENT PARTIAL NIGHT LANE CLOSURE AT LEBUHRAYA TUN DR. LIM CHONG EU
3 Apr
2026
16 May
2026

Activity Time
Piloting & Utility Detection

Description

Activity

Please be informed that a long-term partial nighttime lane closure along the Lebuhraya Tun Dr. Lim Chong Eu will be implemented from 3 April 2026 to 16 May 2026, between 12:00 AM (midnight) and 6:00 AM, over a period of 44 days.


LONG-TERM INTERMITTENT PARTIAL NIGHT LANE CLOSURES ALONG JALAN SULTAN AZLAN SHAH (TERMINAL BAS SG. NIBONG – JPJ BATU UBAN)
8 Apr
2026
30 Jun
2026

Activity Time
10.00PM – 5.00AM

Description

Please be informed that long-term intermittent partial night lane closures along Jalan Sultan Azlan Shah will be implemented from 8 April 2026 to 30 June 2026. The closure will be implemented from 10:00 PM to 5:00 AM, over a period of 84 days.

Activity

Tree Cutting And Tansplanting Work


LONG TERM INTERMITTENT PARTIAL LANE CLOSURES ALONG JALAN TUN DR AWANG (OPPOSITE CAWAN KUEY & SAJIAN – FUTSAL COURT)
30 Mar
2026
15 Jun
2026

Activity Time
8.00AM – 4.00PM

Description

Please be informed that long-term intermittent partial lane closures along a stretch of Jalan Tun Dr Awang (towards Bayan Lepas) will be implemented from 30 March 2026 to 15 June 2026. The closure will be implemented from 8:00 am to 4:00 pm, over a period of 78 days.

Activity

Tree Cutting, Drainage Relocation And Road Widening.


LONG-TERM INTERMITTENT NIGHT CLOSURES (JALAN TUN DR AWANG – JALAN MAHSURI)
1 Apr
2026
31 Jul
2026

Activity Time
10.00PM – 5.00AM

Description

Please be informed that a long-term partial nighttime lane closure at the intersection of Jalan Tun Dr. Awang and Jalan Mahsuri will be implemented from 1 April 2026 to 31 July 2026.The closure will be carried out between 10:00 pm and 5:00 am, over a period of 122 days.

Activity

Identify And Relocation Utilities


PILOTING AND RELOCATION UTILITIES WORK (SPICE AQUATIC CENTRE – SUNGAI RELAU)
1 Apr
2026
31 Jul
2026

Activity Time
10.00PM – 5.00AM

Description

Please be informed that long-term intermittent night lane closures along a stretch of Jalan Tun Dr Awang (towards KOMTAR) and Jalan Mahsuri, will be implemented from 1 April 2026 to 31 July 2026.The closures will be carried out between 10:00 pm and 5:00 am, over a period of 122 days.

Activity

Identify And Relocation Utilities


LONG-TERM INTERMITTENT NIGHT CLOSURES ON JALAN TUN DR AWANG (SPICE AQUATIC CENTRE)
1 Apr
2026
31 Jul
2026

Activity Time
10.00PM – 5.00AM

Description

Please be informed that long-term intermittent night lane closures along a stretch of Jalan Tun Dr Awang (both directions), will be implemented from 1 April 2026 to 31 July 2026. The closures will be carried out between 10:00 pm and 5:00 am.

Activity

Identify And Relocation Utilities


LEFT LANE CLOSURE ON JALAN SULTAN AZLAN SHAH FOR TREE CUTTING, ROAD WIDENING AND DRAINAGE WORKS (GELUGOR)
1 Apr
2026
30 Jun
2026

Activity Time
24 Hours

Description

Please be informed that a long-term lane closures on Jalan Sultan Azlan Shah will be implemented 24 hours a day from 1 April 2026 to 30 June 2026, over a period of 91 days.

Activity

Tree Cutting, Road Widening And Drainage Works.


LONG-TERM INTERMITTENT PARTIAL LANE CLOSURES ALONG JALAN SULTAN AZLAN SHAH (SUNNY POINT – JPJ BATU UBAN)
8 Apr
2026
15 May
2026

Activity Time
10.00PM – 5.00AM

Description

Please be informed that long-term intermittent partial lane closures along a stretch of Jalan Sultan Azlan Shah (both directions) will be implemented from 8 April 2026 to 15 May 2026. The closure will be implemented from 10:00 pm to 5:00 am, over a period of 38 days.

Activity

Drainage And Road Widening Works


LONG-TERM INTERMITTENT PARTIAL LANE CLOSURES ALONG JALAN SULTAN AZLAN SHAH (SUNNY POINT – JPJ BATU UBAN)
8 Apr
2026
15 May
2026

Activity Time
8.00AM – 4.00PM

Description

Please be informed that long-term intermittent partial lane closures along a stretch of Jalan Sultan Azlan Shah (both directions) will be implemented from 8 April 2026 to 15 May 2026. The closure will be implemented from 8:00 am to 4:00 pm, over a period of 38 days.

Activity

Drainage And Road Widening Works