Jalan Tun Razak (Ampang Park)

30 September 2018

Demolition works of former Ampang Park Shopping Centre taking place next to the …

Jalan Raja Muda Abdul Aziz (Kampung Baru North)

30 September 2018

Strutting works for the Sungai Bunus downstream sump at the Kampung Baru North M…

Jalan Tun Razak (Intervention Shaft 1)

30 September 2018

Aerial view of the excavation works at the Intervention Shaft 1 site.…

Jalan Kuchai Lama (Kuchai Lama)

30 September 2018

Piers construction and shoring system works at the Kuchai Lama MRT Station site.…

Jalan Tun Razak (Titiwangsa)

30 September 2018

Rebar works for the concourse slab level of the Titiwangsa MRT Station.…

Jalan Sultan Azlan Shah (Sentul West)

30 September 2018

Overhead view of backfilled roof slab and traffic management at the Sentul West …

Jalan Jinjang Permai 2

29 September 2018

Aerial view of preparation works for segmental box girder launching on Jalan Jin…

Persiaran Dagang (Sri Damansara)

31 August 2018

Aerial view of pier columns construction at the Sri Damansara East MRT Station s…

Jalan Serdang Raya (Serdang Raya South)

31 August 2018

Aerial view of pier construction works at the Serdang Raya South MRT Station sit…

Jalan Kuala Selangor (Sri Damansara)

31 August 2018

Aerial view of pier construction at Sri Damansara West MRT Station site.…

Jalan Serdang Raya (Serdang Raya North)

31 August 2018

Preparation for ground platform and access for launching work at the Serdang Ray…

Jalan Kuching

31 August 2018

Aerial view of soil investigation works at the median of Jalan Kuching.…

Jalan Sungai Besi (Sungai Besi)

31 August 2018

Aerial view of pier column and pier head construction at the Sungai Besi MRT Sta…

Kampung Malaysia Raya

31 August 2018

Aerial view of pile cap and pier works at Kampung Malaysia Raya…

Putrajaya Sentral

31 August 2018

Pier head construction at the Putrajaya Sentral MRT Station site.…