ProjectsPutrajaya LineProject Updates

Project Updates

The Putrajaya Line Project Updates provides the latest project construction progress updates based on the type of alignment and location of the sites. You may also view the locations and status of project from our Project Interactive Map.

Sungai Besi Air Force Base (Bandar Malaysia North)

July 2018

Concourse level slab construction at the Bandar Malaysia North MRT Station site.…

Jalan Sultan Azlan Shah (ES1,North Portal)

July 2018

Aerial view of Escape Shaft 1 site.…

Sungai Besi Airforce (Bandar Malaysia South)

July 2018

Aerial view of the Bandar Malaysia South MRT Station site.…

Sungai Besi Airforce (Bandar Malaysia North)

July 2018

Aerial view of the ongoing base slab construction at the Bandar Malaysia North M…

Jalan Kampung Batu (Kampung Batu)

July 2018

Preparation for segmental box girder launch at the Kampung Batu MRT Station site…

Jalan Kuchai Lama (Kuchai Lama)

July 2018

Pile cap construction works at the Kuchai Lama MRT Station site.…

Jalan Conlay (Conlay)

July 2018

Installation work of construction decking at the Conlay MRT Station site.…

Jalan Chan Sow Lin (Chan Sow Lin)

July 2018

Aerial view of the Chan Sow Lin MRT Station site.…

Jalan Binjai (KLCC East)

July 2018

Aerial view of the KLCC East MRT Station site.…

Persiaran Sierra Utama (16 Sierra)

July 2018

Trestle tower assembly works for the T-beam launching for the 16 Sierra MRT Stat…

Jalan Tun Razak (Ampang Park)

July 2018

Aerial view of the ongoing rebar fabrication works for the roof slab at the Ampa…

Jalan Gurney (Escape Shaft 2)

July 2018

Aerial view of secant bored pile works at the Escape Shaft 2 site.…

Persiaran Alpinia (16 Sierra)

July 2018

Aerial view of sheet piling and drainage enhancing works along Persiaran Alpinia…

Jalan Kepong (Sri Delima)

July 2018

Aerial view of bored piling works and piers construction at the Sri Delima MRT S…

Jalan Kepong (Jinjang)

July 2018

Installation of T-beam for the Jinjang MRT Station.…