December 14, 2012
Electricity Supply Agreement Between Mrt Corp And Tnb

Electricity Supply Agreement Between Mrt Corp And Tnb

THE Klang Valley MRT project achieved another milestone when an Electricity Supply Agreement was signed between Mass Rapid Transit Corporation Sdn Bhd (MRT Corp) and Tenaga Nasional Berhad (TNB) on 14 December 2012.
November 22, 2012
First Tunnel Boring Machine Ready For Action

First Tunnel Boring Machine Ready For Action

Engineers of MRT Corp, together with those from MMC-Gamuda successfully conducted at a Factory Acceptance Test at Herrenknecht AG, the manufacturer of the TBM, at Schawanau, Germany.
October 23, 2012
Thumbs Up From Students of SRJK (C) Jalan Davidson on The MRT Project

Thumbs Up From Students of SRJK (C) Jalan Davidson on The MRT Project

Mass Rapid Transit Corporation Sdn. Bhd. (MRT Corp) is committed to cultivating and attracting the public, especially young people, to use public transportation particularly rail transport. As part of this commitment, a two-day awareness campaign was conducted at SRJK(C) Jalan Davidson, Kuala Lumpur, to educate students on the importance of an effective urban rail transportation system.
October 18, 2012
MRT V2 Work Package Media Briefing

MRT V2 Work Package Media Briefing

Mass Rapid Transit Corporation Sdn. Bhd. (MRT Corp) is pleased to announce that works on MRT V2 viaduct by Gadang Engineering (M) Sdn. Bhd has commenced.
August 14, 2012

Media Briefing on Alternative Routes During The MRT Construction

A series of alternative routes at the various MRT construction stretches, likely to result in congestion, have been identified by Mass Rapid Transit Corporation Sdn. Bhd. (MRT Corp) and its Project Delivery Partner (PDP), MMC Gamuda KVMRT (PDP) Sdn. Bhd., to minimise potential traffic inconvenience to road users during the project’s construction.
August 10, 2012

MRT V3 Work Package Media Briefing

Following the announcement of the MRT project moving from preparatory works to active construction phase earlier this month, Mass Rapid Transit Corporation Sdn. Bhd. (MRT Corp) is pleased to announce that yet another construction work package - the MRT V3 viaduct work - willcommence this month.
August 1, 2012

MRT Project Moves Into Active Construction Phase

Mass Rapid Transit Corporation Sdn. Bhd. (MRT Corp) is pleased to announce that the country’s largest infrastructure project, the MRT Sungai Buloh - Kajang (SBK) Line, is on schedule, and has now moved from preparatory works to an active construction phase.
July 31, 2012

NTV7 Breakfast Show Interview with MRT Corp

On July 31, 2012, NTV 7 Breakfast Show interviewed Encik Amir Mahmood Razak, Director of Strategic Communications and Public Relations of Mass Rapid Transit Corporation Sdn. Bhd. (MRT Corp) on the Mass Rapid Transit (MRT) Project.
July 21, 2012

Bernama TV BizTalk Interview with MRT Corp

On July 31, 2012, Bernama TV’s BizTalk interviewed Dato’ Azhar Abdul Hamid, CEO of Mass Rapid Transit Corporation Sdn. Bhd. (MRT Corp) on the Mass Rapid Transit (MRT) Project.