Traffic Announcement
CONTINUATION OF LEFT LANE CLOSURE AT JALAN LINGKARAN DALAM, JOHOR BAHRU (NEAR SHELL PETROL STATION)
2026
2026
Activity Time
24 Hours
Description
Please be informed that the left lane closure at Jalan Lingkaran Dalam (near Shell petrol station), will be extended from 21 July 2026 to 30 August 2026. The construction works will be carried out 24 hours, for one (1) month and ten (10) days.
Activity
To facilitate machinery mobilization works, drainage works, Mill & Pave works, road marking works, and other RTS Link project-related works.
LONG TERM INTERMITTENT NIGHT-TIME CLOSURE OF THE EXIT ROAD IN FRONT OF MULTI-STOREY CAR PARK. (PENANG INTERNATIONAL AIRPORT)
2026
2026
Activity Time
9.00PM – 5.00AM
Description
Please be informed that a long-term intermittent partial night lane closure will be implemented on Jalan Lapangan Terbang Antarabangsa Pulau Pinang from 16 July 2026 until 17 October 2026. The activity will take place from 9:00 PM to 5:00 AM, over a period of 93 days.
Activity
CONSTRUCTION WORK FOR LRT RUNWAY
LONG-TERM INTERMITTENT PARTIAL NIGHT LANE CLOSURE ALONG TUN DR. LIM CHONG EU EXPRESSWAY
2026
2026
Activity Time
10.00AM – 4.00PM
Description
Please be informed that a long-term periodic partial lane closures along Tun Dr. Lim Chong Eu Expressway will be implemented from 12 July to 30 September 2026, from 10:00 AM to 4:00 PM daily, over a period of 80 days.
Activity
TREE CUTTING WORKS
LONG-TERM PARTIAL MOTORCYCLE LANE CLOSURES ON JALAN SUNGAI PINANG
2026
2026
Activity Time
12.00 am – 6.00 am
Description
Please be informed that a long-term partial closure of the motorcycle lane of Jalan Sungai Pinang will be implemented from 6 July to 4 August 2026, between 12:00 midnight and 6:00 AM, over a period of 29 days.
Activity
PILOTING & UTILITY DETECTION
LONG-TERM INTERMITTENT PARTIAL DAY LANE CLOSURE ALONG JALAN SULTAN AZLAN SHAH (BOTH DIRECTIONS)
2026
2026
Activity Time
9.00 am – 5.00 pm
Description
Please be informed that long term intermittent partial day lane closure on Jalan Tengah will be implemented from 7 July 2026 to 30 September 2026. The closure will be implemented between 9:00 am and 5.00 pm, over a period of 85 days.
Activity
TREE CUTTING, DRAINAGE RELOCATION AND ROAD WIDENING WORKS
LONG-TERM INTERMITTENT PARTIAL NIGHT LANE CLOSURE ALONG JALAN TENGAH (BOTH DIRECTIONS)
2026
2026
Activity Time
10.00PM – 5.00AM
Description
Please be informed that long term intermittent partial night lane closure on Jalan Tengah will be implemented from 7 July 2026 to 30 September 2026. The closure will be implemented between 10:00 pm and 5.00 am, over a period of 85 days.
Activity
TREE CUTTING, DRAINAGE RELOCATION AND ROAD WIDENING WORKS
LONG-TERM INTERMITTENT PARTIAL DAY LANE CLOSURE ALONG JALAN SULTAN AZLAN SHAH (BOTH DIRECTION)
2026
2026
Activity Time
9.00 am – 5.00 pm
Description
Please be informed that long-term intermittent partial day lane closure at night will be implemented along Jalan Sultan Azlan Shah (both directions) from 7 July 2026 to 30 September 2026. The closure period will be between 9:00 am and 5:00 pm, over a period of 85 days.
Activity
TREE CUTTING, DRAINAGE RELOCATION AND ROAD WIDENING WORKS.
LONG-TERM INTERMITTENT PARTIAL NIGHT LANE CLOSURE ALONG JALAN SULTAN AZLAN SHAH (BOTH DIRECTIONS)
2026
2026
Activity Time
10.00PM – 5.00AM
Description
Please be informed that long-term intermittent partial night lane closure at night will be implemented along Jalan Sultan Azlan Shah (both directions) from 7 July 2026 to 30 September 2026. The closure period will be between 10:00 pm and 5:00 am, over a period of 85 days.
Activity
TREE CUTTING, DRAINAGE RELOCATION AND ROAD WIDENING WORKS
LONG-TERM INTERMITTENT PARTIAL DAY LANE CLOSURE ALONG JALAN SULTAN AZLAN SHAH (BOTH DIRECTIONS)
2026
2026
Activity Time
9.00 am – 5.00 pm
Description
Please be informed that long-term intermittent partial day lane closure will be implemented along Jalan Sultan Azlan Shah, between Dynacraft Industries and B Braun Medical Industrial, as well as between Robert Bosch (M) and Cortex, from 6 July 2026 to 30 September 2026. The closure period will be between 9:00 am and 5:00 pm, over a period of 86 days.
Activity
TREE CUTTING, DRAINAGE RELOCATION AND ROAD WIDENING WORKS