Traffic Announcement
SHORT – TERM INTERMITTENT PARTIAL LANE CLOSURE ALONG JALAN HAJI AHMAD (TUN DR. LIM CHONG EU EXPRESSWAY)
2026
2026
Activity Time
9.00 am – 5.00 pm
Description
Please be informed that a short-term intermittent partial lane closure along Jalan Haji Ahmad will be implemented from 12 September 2026 until 16 September 2026. The closure will be implemented from 9:00 AM to 5:00 PM, over a period of 4 days. The traffic management plan is as follows:
Activity
UTILITY RELOCATION WORKS
CONTINUATION OF INTERMITTENT FULL ROAD CLOSURES AT JALAN TEBRAU (KOTA TINGGI-BOUND) AND JALAN TUN ABDUL RAZAK (SKUDAI/ SENAI-BOUND), JOHOR BAHRU
2026
2026
Activity Time
10.00 PM - 5.30 AM
Description
Please be informed that there will be intermittent full road closures along Jalan Tebrau (Kota Tinggi-bound) and Jalan Tun Abdul Razak (Skudai/ Senai-bound) will be extended from 1 September 2026 to 30 September works will be carried out from 10.00 PM to 5.30 AM for one (1) month.
Activity
To facilitate construction machinery mobilization, road works, drainage works, utilities work, parapet wall installation works and other RTS Link project-related works.
LONG-TERM PARTIAL ROAD CLOSURE ALONG JALAN MAGAZINE
2026
2026
Activity Time
24 Hours
Description
Please be informed that short-term lane closure at Jalan Magazine will be implemented 24 hours daily, commencing at 10:00 PM on 14 September 2026 until 5:00 AM on 5 October 2027, over a period of 21 days. The traffic management plan is as follows:
Activity
ROAD WIDENING AND UTILITIES RELOCATION WORKS
LONG-TERM LANE DIVERSION ON JALAN SULTAN AZLAN SHAH (TOWARDS TELUK KUMBAR) (BAYAN LEPAS)
2026
2027
Activity Time
24 Hours
Description
Please be informed that long-term lane diversion along a stretch of Jalan Sultan Azlan Shah will be implemented from 12 September 2026 to 31 July 2027, over a period of 322 days. The traffic management plan is as follows:
Activity
CONSTRUCTION WORKS AT THE MEDIAN FOR LRT PIER
LONG-TERM INTERMITTENT PARTIAL LANE CLOSURES ALONG JALAN SULTAN AZLAN SHAH (SUNNY POINT JUNCTION – USM FIELD)
2026
2026
Activity Time
8.00AM – 4.00PM
Description
Please be informed that long-term intermittent partial lane closures along Jalan Sultan Azlan Shah will be implemented from 16 September 2026 to 15 December 2026. The closure will be implemented from 8:00 AM to 4:00 PM, over a period of 90 days. The traffic management plan is as follows:
Activity
RELOCATION OF DRAINAGE AND ROAD WIDENING WORKS
SHORT-TERM LANE CLOSURE ON GAT LEBUH CECIL (MACALLUM) (LEBUHRAYA TUN DR. LIM CHONG EU)
2026
2026
Activity Time
10.00PM – 5.00AM
Description
Please be informed a short-term lane closure at Gat Lebuh Cecil will be implemented for a period of 3 days, commencing at 10:00 PM on 4 September 2026 until 5:00 AM on 7 September 2026. The traffic management plan is as follows:
Activity
UTILITY RELOCATION (PBA 1.2m Waterpipe)
SHORT-TERM ROAD CLOSURE ON GAT LEBUH CECIL & TUN DR. LIM CHONG EU HIGHWAY
2026
2026
Activity Time
10.00PM – 5.00AM
Description
Please be informed a short-term partial lane closure at Tun Dr. Lim Chong Eu Expressway and Gat Lebuh Cecil will be implemented for a period of 3 days, commencing at 10:00PM on 07 September until 5:00AM on 10 September 2026. The traffic management plan is as follows:
Activity
UTILITY RELOCATION FOR 1.2m WATERPIPES
LONG-TERM PERIODIC PARTIAL ROAD CLOSURE ALONG JALAN SULTAN AZLAN SHAH
2026
2026
Activity Time
10.00PM – 5.00AM
Description
Please be informed a long-term intermittent partial night lane closures along Jalan Sultan Azlan Shah will be implemented from 1 September 2026 to 6 October 2026. The closure will be implemented from 10:00 AM to 5:00 AM, over a period of 35 days. The traffic management plan is as follows:
Activity
IDENTIFY AND RELOCATION UTILITIES
LONG-TERM INTERMITTENT NIGHT CLOSURES ON JALAN MAHSURI (JALAN TUN DR. AWANG)
2026
2026
Activity Time
10.00PM – 5.00AM
Description
Please be informed a long-term intermittent partial night lane closure along the Jalan Mahsuri will be implemented from 2 September 2026 to 31 October 2026. The closure will be implemented from 10:00 PM to 5:00 AM, over a period of 59 days. The traffic management plan is as follows:
Activity
UTILITY RELOCATION WORKS